The client approached us to provide a localized solution to the non-critical electrical infrastructure. The main concern of the client was that the panels needed to meet the standards of multiple countries standards. 

​

The project consisted of designing, assembling and installing 29 low voltage panels with a rating of up to 5000A. We also designed and installed 2 Medium voltage (11Kv) panels ready for utility connection to the site along with 2 x 20-meter 5000A aerial bus duct runs.

 

​

​

​

​

PROJECT FACTS

Industry

Defence

Services used

Design, Procurement, Panel Assembly, Installation

Brands Used

Schneider

SOLUTION PROCESS

Business Graphs

1

What was the aim?

The main contractor identified they would need a vendor who understood the local and international standards to achieve engineering approval 

2

What was our solution?

Design and install a hybrid solution panel with a range of components from different markets

3

What did we achieve?

The panels were installed and brought into service without issue. 